Wastewater treatment plant at Turów Power Plant - reinforced concrete and earth works.
16.07.2021
Work is in progress at the construction site at the Turów Power Plant. Currently, reinforced concrete works are underway at the Node E, so far, foundations and reinforced concrete tanks have been made, including: raw sewage, ultrafiltration waste water tanks and a concentrate flow tank after the reverse osmosis installation. Dampproof insulation and backfilling of foundations are made. The front for disassembly of technological pipelines on the existing part of the Turów Power Plant is also being prepared, where new flyovers will be built and technological installations connecting Node E and Node D (sulphate precipitation node) will be installed. At Node D, the area is prepared for earthworks, which was preceded by extensive deforestation. In addition, we are carrying out preparatory work for network spacers enabling entry to Node D.